4/8 Update

Asalamualaikum everyone!

PECO lines are in alhamdulillah. However, we are still waiting for energizing the bulding.

The plumbing work is on going, and we have added 2 wudu stations to each men and womens bathrooms.

We are currently doing some design changes to the reflected ceiling plan (lighting fixtures and type of ceiling), and site grading is also taking place.