6/1 Update

Asalamualaikum everyone,

Here are the recent updates on the masjid construction:

  • Roof has been succesfully completed

  • We have passed the rough inspection for the plumbing from the township

  • We are currently working on finishing up the electrical and HVAC roughens

  • As we were completed the as-builts the finished floor elevation was found to be less than the design elevation.

  • We are working with the contractor and site engineer to come up with the remedy to ensure the building will be waterproof